NEW DELHI, Dec 13: Less than 25 per cent of the solar power projects sanctioned by the centre have so far been actually commissioned, the government told the Rajya Sabha on Tuesday.
According to the details submitted by the Minister for New and Renewable Energy RK Singh in the Upper House, the Union government has so far sanctioned the development of solar projects with a capacity of nearly 39,000 MW but only a fourth have actually been commissioned so far.
Under the “Scheme for Development of Solar Parks and Ultra Mega Solar Power Projects”, a total of 57 solar parks of aggregate capacity of 39,285 MW were sanctioned until November-end. However, only solar power projects of 10,027 MW have been commissioned in these parks.
Citing reasons for the shortfall, Mr. Singh said some solar parks were cancelled due to their “slow progress” but key challenges in this scheme included challenges with acquisition of land with clear title; a “mismatch” in the time taken to set up a project and the infrastructure to route the power produced to the grid; “environmental issues” and the halt in economic activity due to COVID-19.
In his reference to “environmental issues,” Mr. Singh mentioned the “Great Indian Bustard (GIB) issue.” In recent years, the habitat of the GIB — a critically endangered species with numbers less than 200 in Rajasthan — has been encroached upon by solar-power projects particularly by transmission lines that endanger the bird.
The Supreme Court last April, had directed that power companies lay underground cables in solar parks in Rajasthan though few companies have actually complied. Mr. Singh’s Ministry had told the Supreme Court in December 2021 that laying underground cables were impractical and would greatly raise the cost of solar power.
India had committed to installing 175,000 MW of renewable energy by 2022 of which 100,000 MW was to be solar power. As of October 2022, as much as 61,000 MW of solar power had been installed, the minister said.
(Manas Dasgupta)