Ahmedabad, 30 April 2025: Adani Power Ltd. [“APL”], a part of Adani portfolio of companies, today announced the financial results for the fourth quarter ended 31st March 2025. Commenting on the results, Mr. S B Khyalia, CEO, Adani Power Limited, said, “Adani Power has posted ever higher operating and financial performance for FY 2024-25, aptly demonstrating the strength and resilience of the Adani Portfolio companies. As we progress quickly in the next phase of capacity expansion, we are prioritising capital and cost efficiencies to sharpen our competitive edge and extend our sectoral leadership across key parameters.  We are employing our deep, cross-domain expertise to make the business future ready to continue delivering superior returns over the long term.  Our unrelenting commitment to sustainability, which has seen us rank among the best thermal power producers in the world on several counts, will continue to guide us on our growth journey.”

Operating performance

Parameter FY25 FY24 Q4 FY25 Q4 FY24
Installed Capacity (MW) 17,550 15,250 17,550 15,250
Plant Load Factor 70.5% 64.7% 74.2% 71.5%
Units Sold (BU) 95.9 79.4 26.3 22.2

MW: Mega Watts; BU: Billion Units

Business updates

Financial performance

Particulars

(Rs. in Crore)

FY25 FY24 Change +/- Q4 FY25 Q4 FY24 Change +/-
Continuing Revenue from Operations(1) 54,502.81 49,667.82 9.73% 14,145.31 13,288.30 6.45%
Continuing Other Income(2) 1,969.91 1,292.06 52.46% 377.08 498.97 (24.43%)
Total Continuing Revenue 56,472.72 50,959.87 10.82% 14,522.39 13,787.26 5.33%
Total Reported Revenue 58,905.83 60,281.48 (2.28%) 14,535.60 13,881.52 4.71%
Continuing EBITDA 21,575.07 18,789.32 14.83% 5,097.62 5,273.31 (3.33%)
Reported EBITDA 24,008.18 28,110.93 (14.59%) 5,110.83 5,367.57 (4.78%)
Continuing Profit Before Tax 13,926.40 11,469.90 21.42% 3,248.07 3,463.68 (6.22%)
Reported Profit Before Tax 16,359.51 20,791.51 (21.32%) 3,261.28 3,557.94 (8.34%)
Tax expenses / (Credit) 3,609.90 -37.28 n.m. 662.05 820.70 (19.33%)
Profit After Tax 12,749.61 20,828.79 (38.79%) 2,599.23 2,737.24 (5.04%)

(1), (2): Continuing Operating Revenues and Continuing Other Income exclude prior period income recognition on account of coal shortfall claims and late payment surcharge.

* n.m.: not meaningful

Key financial highlights

Project Updates

APL has undertaken expansion of its existing capacities from 17,550 MW to 30,670 MW by 2030 through a mix of brownfield and greenfield projects. It is currently constructing three brownfield projects of 1,600 MW each at its existing power plant locations at Singrauli (Mahan) in Madhya Pradesh, and Raipur and Raigarh in Chhattisgarh. Apart from this, it is also reviving the stalled 1,320 MW expansion project of Korba Power Ltd. (erstwhile Lanco Amarkantak Power Ltd.) at Korba in Chhattisgarh.

APL already possesses land for expansion of its capacities by 12,520 MW (excluding 600 MW capacity of VIPL), which mitigates one of the major execution risks for projects of this kind. Furthermore, it has taken effective measures to derisk the project supply chain, by giving advance orders for 11,200 MW of main plant equipment comprising 14 sets of 800 MW Ultra-supercritical boilers, steam turbines, and generators to a leading domestic manufacturer. Other major and minor contracts for project supply and execution are also being awarded in a stage-wise manner.

APL is confident of executing these expansion projects within the target timelines and costs by leveraging its project, supply chain, and contract management capabilities in addition to employing its substantial financial resources and highly visible and stable cash flows.

ESG Performance