Mr. S B Khyalia, CEO, Adani Power Limited, said, “Adani Power is well on its way to achieve its generation capacity target of 30+ GW by 2030, with rapid progress in under-construction projects, secure supply chain, and successful bids for long term PPA tie-ups.  We are well-positioned to benefit from the attractive opportunities in the Indian thermal power sector and to support its steadily growing power demand. Our high-quality asset portfolio, operating excellence, and execution capabilities set us apart and help us deliver consistent profitability and cash flows. We are taking steps ranging from backward integration into mining to improve our competitiveness and digitalization of our operations to enhance our future-readiness. Our unceasing focus on our ESG efforts has placed us amongst top 15% of our global peers and earned us international recognition.”

Operating performance

Parameter 9M FY25 9M FY24 Q3 FY25 Q3 FY24
Installed Capacity 17,550 MW 15,250 MW 17,550 MW 15,250 MW
Plant Load Factor 69.3% 62.4% 63.9% 68.6%
Units Sold 69.5 57.1 23.3 21.5

MW: Mega Watts; BU: Billion Units

All-India power demand grew by 4.3% to 393 BU in Q3 FY25 as compared to Q3 FY24. Demand growth was affected marginally due to cold weather. However, demand picked up in the month of December 2024, which registered a growth of 5.7% over December 2023. The cumulative demand for FY 2024-25 till 31st December 2024 was healthy with a growth of 4.6% over the corresponding period of FY 2023-24.  As a result of the slower growth in power demand and an increase in supply, average market clearing price on the Indian Energy Exchange declined by 26% year-on-year to Rs. 3.71/kWh in Q3 FY25. However, with the Government estimating peak power demand reaching 270 GW in the summer of 2025 from 250 GW in 2024, merchant prices are expected to regain strength.

Business updates

Key operating highlights for 9M and Q3 FY25

The newly acquired power plants of Dahanu (“ADTPS”), Moxie Power Generation Ltd. (“MPGL”) and Korba Power Ltd. (“KPL”) contributed to the aggregate power dispatch growth in Q3FY25. The recently concluded quarter also witnessed a growth in power dispatched to the merchant and short-term market, supported by the Company’s competitive advantages in capacity available for generation as well as in fuel sourcing.

APL has also awarded major contracts including main plant equipment supply for its ongoing and upcoming expansion projects, addressing key supply constraints and ensuring smooth and on-time project execution.

Financial performance 

Particulars

(Rs. in Crore)

9M FY25 9M FY24 Change +/- Q3 FY25 Q3 FY24 Change +/-
Continuing Revenue from Operations(1) 40,357.84 36,379.52 10.9% 12,691.83 13,143.34 (3.4%)
Continuing Other Income(2) 1,592.83 793.09 100.8% 741.94 262.13 183.0%
Total Continuing Revenue 41,950.66 37,172.61 12.9% 13,433.76 13,405.47 0.2%
Total Reported Revenue 44,370.23 46,399.96 (4.4%) 14,833.44 13,355.27 11.1%
Continuing EBITDA 16,477.78 13,516.01 21.9% 4,785.50 5,059.37 (5.4%)
Reported EBITDA 18,897.35 22,743.36 (16.9%) 6,185.18 5,009.17 23.5%
Continuing Profit Before Tax 10,678.66 8,006.22 33.4% 2,658.96 3,260.58 (18.5%)
Reported Profit Before Tax 13,098.23 17,233.57 (24.0%) 4,058.64 3,210.38 26.4%
Tax expenses / (Credit) 2,947.85  (857.98) n.m. 1,118.57 472.42 136.8%
Profit After Tax 10,150.38 18,091.55 (43.9%) 2,940.07 2,737.96 7.4%

(1), (2): Continuing Operating Revenues and Continuing Other Income exclude prior period income recognition on account of coal shortfall claims and late payment surcharge.

* n.m.: not meaningful

Key financial highlights for 9M and Q3 FY 2024-25