Site icon Revoi.in

Safe Evacuation of All Tunnel Trapped Workers Assured but Timeframe Uncertain

Social Share

Manas Dasgupta

NEW DELHI, Nov 24: With unforeseen snags developing every now and then in the operation to rescue the 41 workers trapped in the collapsed tunnel in Uttarakhand for the last 12 days, authorities are keeping their fingers crossed when will be the D-day finally arrive but underline with confidence that all the workers will come out safely sooner rather than later.

Even as some of the officials said no much progress in drilling operation could be made since Wednesday due to various snags developing one after another, some others said all the unforeseen snags had been removed as of now and the drilling operation was set to resume and was expected to be completed in the next few hours.

Admitting that some 12 to 15 metres of drilling was still to be completed with the next four metres could be very crucial, the officials refused to give any timeframe because of the unexpected hurdles have been delaying the work. But there may be light at the end of the tunnel as ground penetrating radar has revealed that there are likely to be no major metal obstacles for the next five metres that will be drilled in the next few hours.

The officials do not expect much trouble in the last five metres or so as the obstacles should by and large of only of loose soil and could be penetrated quickly. The officials also said if all goes well, pushing in two more pipes may be enough to reach the labourers.

“When the welding of the new pipe, that we will laying down now, shall be done (which takes around 2 hours), we hope that we push the pipe further this time and no hurdle is there to stop it,” says Additional Secretary Technical, Road and Transport Mahmood Ahmed.

ONGC director Sanjay Bhatt who is present at the site, on Friday afternoon said, “We are hopeful that the rescue operation will be concluded and the workers brought out safely by today. As of now, there is no major hindrance to the operation and everyone is hopeful that the workers will be rescued by this evening.” Officials, at an afternoon news briefing, said the technical problem that stalled the drilling on Wednesday had been set right, and the operation would begin in the next couple of hours.

Himalayan geology is not a precise science and many roadblocks have come in the way of the multi-agency, 12-day rescue operation, so far.

Despite all the optimistic views, no official, however, is overlooking the intricacies of the Himalayan geology. “The Himalayan geology is not as predictable as people think,” National Highways Authority of India member (admin) Vishal Chauhan said. Addressing a press meet over the ongoing progress of the rescue work, Mr Chauhan said, “Himalayan geology is unpredictable and several roadblocks came in the way, despite the best efforts of all the government and private agencies.

Addressing a press conference jointly, Mr Ahmed and Uttarakhand Secretary Neeraj Khairwal, who is the nodal officer for the rescue operation, said the auger machine hit a metal pipe on Thursday evening which wrapped itself around the drilling blades. They said many hours had to be spent repairing the machine’s blades, strengthening the platform on which the machine is operating and removing the metal girders and pipes which were obstructing the operation.

Mr Ahmed pointed out that before drilling resumes, some welding will need to be done, which will take about two hours. He explained that the welding process was a complicated one and needs to be done carefully so that the area being welded stays strong.

Explaining one reason for the delay, Mr Khairwal said, “Since 4 pm yesterday to now, time was spent strengthening the platform, which had moved. The mouth of one of the 800 mm pipes that had been pushed in by us had narrowed and we actually had to cut about 1.2 metres of it. Three metres of pipe had been pushed in yesterday in addition to the 45 metres before, but 1.2 metres of this had to be cut because the auger would not have been able to proceed further.” The distance covered by the pipes is currently 46.8 metres because 1.2 metres had to be removed.

Mr Khairwal said cutting the pipe as well as vertical pipes from the tunnel’s ceiling that were obstructing the drill took seven to eight hours and while people thought that the auger machine had broken down, that was not the case. In the meantime, a team of ground penetrating radar experts was called in and one of their men took 45 minutes to travel inside the pipes for 45 metres and take their measuring machine inside.

“The narrowing of the end of the pipe meant they could not say this with 100% accuracy but what they are expecting is that there is no continuous metal object, like girders, pipes and metal plates, in the next 5.4 metres. They have pointed out some other hurdles, but this is good news,” he emphasised.

The bigger 700 mm auger is going to be used now that the pipe has been cut, Mr Khairwal said, adding that the hope is that the work will be completed at the earliest. “The first hour of drilling after the welding is done will be critical,” he said.

Mr Ahmed said, if all goes well, pushing in and welding two pipes with a length of 6 metres each should be enough to “break through” to the workers but this is an assumption based on their assessments. He cautioned, however, that obstacles and hurdles can still appear at any point. To a question on whether teams could reach the workers by Saturday morning, the official said it could happen even sooner if everything goes smoothly.

The under-construction tunnel in Uttarkashi is part of the ambitious Char Dham project, a national infrastructure initiative to enhance connectivity to the Hindu pilgrimage sites of Badrinath, Kedarnath, Gangotri, and Yamunotri. The labourers got trapped when a portion of the tunnel had collapsed on November 12.